Hi faraaz,

The baseline of a task will be shown only if the task has a “planned” property, which determines the dateStart and dateEnd of the baseline.

Please see the example on our site – https://www.htmlelements.com/demos/gantt/task-baseline/

 

Best Regards,
Ivan Peevski

Smart UI Team
https://www.htmlelements.com/