    Hey Team,

    I have encountered with an issue, when having the week view, it has the header that displays the month and the dates that are present in the week “apr 1-apr 7″but when I see the actual days in that week column , the days are according to the calendar. I want the header to contain the same dates that are part of that week. But this is not happening. Can someone help me fix this issue. Provided the link for better understanding

    #110657
    Markov
    Keymaster

    Hi,

    You can use the timelineHeaderFormatFunction(date, headerType, isSubHeader, dateString) and return the result to be displayed in that header.

    Regards,
    Markov