  • #108818
    faraaz
    Participant

    Hi,

    While trying to create connections between task through dependency tab, by default the connection goes to first task/project or overall timeline(default to id 0) but not with the given name, connection type, connection id and lag.

    I tried to create connection from task 2 to task 3(connection id: 5-3-1), but it creates connection from project 1 to task 2(connection id: 0-3-1) as end-to-start connection type.

    https://www.htmlelements.com/demos/gantt/auto-schedule/

    #108824

    Hi,

    Many thanks for reporting the problem, I have opened a work item for it!
    Meanwhile, if you have any questions, do not hesitate to contact us!

    Best Regards,
    Svetoslav Borislavov

    Smart UI Team