JavaScript UI Libraries & Blazor Components Suite – Smart UI › Forums › Gantt › Task Baseline not working › Reply To: Task Baseline not working
September 20, 2023 at 6:47 am
#108730
svetoslav_borislavov
Participant
Hi,
You should have dateStart and dateEnd in the task object, the label can be skipped and the default label will be ‘Unassigned’
Here is an example with similar task to yours:
https://codepen.io/dkeamcaksoem/pen/jOXaXxe
Best Regards,
Svetoslav Borislavov
Smart UI Team
https://www.htmlelements.com/